Active Projects
Active projects in Wastewater Section - Ahwaz | ||||||
---|---|---|---|---|---|---|
No. | Projects | Execution place | starting date | finishing date | contractor | financing |
1 | Ahvaz Eastern Wastewater Plant | Ahvaz | 1388/02/22 | 1390/08/20 | Joint Venture Mushrif-Kayson | national |
2 | Execution of Main line(pipe=1400 mm GRP | Ahvaz | 1392/12/20 | 1393/08/20 | Almas Rah Jonoob | |
3 | Execution of wastewater transmission line(part B) | Ahvaz | 1392/5/14 | 1393/7/14 | Parto Sanat Khoshnam | |
4 | Execution of completion work -wastewater line 2000 mm | Ahvaz | 1394/06/07 | 1395/12/07 | Solok Sazeh Gonoob | |
5 | Execution of completion work -wastewater line 1200 mm | Ahvaz | 1394/09/22 | 1395/03/22 | Parto Sanat Khoshnam | |
6 | Execution of collecting network and sewage branches in Modares | Ahvaz | - | - | Avaj Rah Jonoob | consignment |
7 | Execution of collecting network and sewage branches in Zeragan | Ahvaz | 1394/08/24 | 1395/04/24 | Rashid Kar Khozestan | current |
8 | Execution of sewage main line 315 mm -2000 units for Oil Co. | Ahvaz | 1395/04/14 | 1395/08/14 | Bana Ab Karkheh | |
9 | Execution of sewage main line 500 mm - 2000 units for maskan Mehr | Ahvaz | 1395/04/06 | 1395/07/06 | Behrooz Bana Ahvaz | |
10 | Execution of collecting network and sewage branches in Mehr Shahr | Ahvaz | - | - | Done by Co-operative society | Co-operative |
11 | Execution of collecting network and sewage branches in Mahdis | Ahvaz | - | - | ||
12 | Execution of completion of water distribution network & parts of sewage household branches - Ramin shahr | Ramin city | 1394/11/20 | 1395/05/20 | Pooyan Sazeh Zigoorat | National |
Active projects in Water Section - Ahwaz |
||||||
---|---|---|---|---|---|---|
No. | Projects | Execution place | starting date | finishing date | contractor | financing |
1 | Network Corrections in Ostadan District | Ahvaz | 1394/07/01 | 1394/09/16 | Farokh Rah Jonoob | Provincial |
2 | Network Execution & water branches in Hasir Abad | Ahvaz | 1394/03/03 | 1394/07/03 | Mahak Izah | |
3 | Execution of Network & branches in Mellat | Ahvaz | 1395/02/13 | 1395/08/13 | Bana Ab Karkheh | |
4 | Execution of completion of water distribution network & parts of potable water household branches - Ramin shahr | Ramin city | 34663 | 1395/02/25 | Avaj Rah Jonoob | National |
5 | Completion of Network Corrections in Kargaran- hamidieh | Hamidieh | 1395/05/15 | 1395/06/30 | 86 Day Company Ahvaz | |
6 | Network Execution & water branches in Beheshti- shayban | Shayban | 1395/04/23 | 1395/06/23 | Avaj Rah Jonoob |